HI-2, 60 MW DC
As the EPC, Moss’ scope of work includes full engineering and construction of both the 60 MW DC PV Plant and 34.5/138kV substation, as well as all sitework, electrical installation, foundation installation, and the installation of SunPower’s Oasis 3 single axis tracker system with SunPower P-Series and E-Series modules.
- 15.90 MW AC, 60 MW DC
- Power Electronics Inverters
- SunPower P-Series & E-Series Modules
- SunPower Oasis 3 single-axis tracker system
- Over 160,000 solar panels
- Sheep grazing will help manage vegetation while supporting local agriculture